ILI of small diameter ethylene pipeline network
Inspection (ILI) of an ethylene pipeline network in the south of France posed several unusual challenges. Geometric and metal loss inspections were required.
Challenges included: small diameter lines combined with rather long sections, the presence of a number of ID restrictions and the requirement to perform all
pigging in a gas (N2) medium. Magnets and metallic components remained in the pipelines from a previous unsuccessful attempt at inspection. The gaseous
medium meant the potential for substantial speed
excursions. Special procedures and customised tool for both cleaning and ILI were developed. Several mobilisations imposed additional logistical
requirements.
Planning for ILI had begun already in 2011, with
focus on performing pigging operations while the lines were temporarily de-commissioned.
First pigging operations began mid-2013 with another vendor – unknown to 3P Services. During the runs serious problems were encountered and the project ran into difficulties with damaged and stuck tools.
Several factors were identified as causing the
problems: the sections were too long, the N2 pressure was not high enough and the presence of heavy wall tee-pieces at valve stations. Since several
attempts had been made using the same
operational settings, it was decided to bring
another ILI vendor to the project.
Pigging method
After consultation, the operator agreed with 3P Services to split the lines into shorter sections and increase pressure to achieve controlled tool runs. Several special pigging procedures as well as
pipeline specific pumping procedures were
developed with focus to achieve tool speeds as constant as possible. Customised cleaning tools were designed and built to recover the magnets and metallic components remaining in the lines.
The method, while seemingly complicated and
laborious on site, did achieve the desired speed
profile. Accelerations at the valve stations were
unavoidable, but substantially mitigated and the
distances where inspection data was impacted were reduced.
Results and experience
Timing was of critical importance due to plant
shutdown periods and all inspections were
successfully completed during the planned operational windows. While some cleaning issues were
occasionally encountered, all ILI data was complete and good quality.
Mechanical parts collected during magnet hunter tool run
Even though the inspections were done at the
specified high pressures, the tools stopped in front of and within valve stations at thick wall tee-pieces. Speed excursions resulted when tools exited the tees. The pigging method with temporary stops to shorten section length proved effective to reduce the length of the excursions and affected ILI data.
Physical performance of the tools was good. Only negligible and normal wear was observed on the PU components and tools could practically immediately be made ready for another run.
Already after the first pigging campaign, the operator performed some field investigations together with the responsible authority, which validated the findings of the inspection reports.
<<< Previous Next >>>
Also in this issue: