There were several significant challenges in the
project including the following:
- The pipeline was constructed using internally uncoated steel pipe: the first such Jet A1 Fuel Service line in the region
- Onerous acceptance criteria: ASTM D5452/IT423 calls for ≤1.0 mg/lit of debris, JIG 1530 requires water content ≤0.1 ppm
- Any non-compliant fuel must be routed back to the refinery by road tankers
- Lack of water in the area determined that it had to be re-used and optimized
- Disposal constraints restricted the chemicals which could be used in the hydrotest water
- The political situation in the region led to delays in construction materials
- Project schedule was critical due the strategic importance of the project
Halliburton developed tailored engineered
solutions to meet these challenges, working with the client as partners during the pre-engineering stages to determine the methodology and basis of construction.
Initial pigging and cleaning of the pipeline was performed in 5 sections: based on availability of water and storage/evaporation ponds. The
pigging sequence was engineered to maximize debris removal and bring final debris amount to below 5 kg per section in order to meet the
cleanliness acceptance criteria.
Approval was gained to use only a biocide
treatment in the hydrotest fill water and to re-use it across the 5 Pipeline Sections. In order to
prevent corrosion of the internal surface of the pipeline after hydrotesting, each section was
dewatered and swabbed, vacuum dried and packed with Nitrogen in a short time frame.
The project was executed by experienced
Halliburton engineers and crew whose detailed pre-engineering and preparations ensured
flawless execution of the pre-commissioning services. Some of the key successes of the
execution include:
- Initial cleaning runs of the 5 sections resulted in a debris level of less than 2 kg per 20 km section
- Filling operations were carried out with minimal air entrapment across all sections
- Hydrotesting required high resolution instrument accuracy, the pipeline operator and Halliburton worked together to establish a standard protocol
- Successfully re-used Hydrotesting water from section to section by analyzing water quality and re-dosing biocide based on results
- Drying acceptance criteria of -20ºC was achieved successfully for the full 132 km pipeline in 12 days using Vacuum Drying
- The final cleaning run recovered less than 450 gm of debris, the acceptance threshold was 36 kg
- Successfully completed final gauge pigging in a single run, only using back-pressure for the complicated terminal end construction pipework
The unique combination of engineering, collaboration with the customer, efficiency of operation and
optimization of schedules resulted in a successfully pre-commissioned pipeline with a record low debris recovery, thus exceeding the customers’ expectations and successfully meeting their goals.